Member Login

Email address required.
Password required.
×

Bliss for shipowners! Damages may be claimed in addition to demurrage for voyage charterparty delay

Posted on: 28 October 2020

In a significant decision for the maritime sector, the English Commercial Court has resolved a much-debated question of answering that an owner can, under certain circumstances, recover damages in addition to demurrage for delay to a vessel under a voyage charterparty,

Background

The dry bulk carrier, Eternal Bliss, shipped a cargo of soybeans from Brazil to China on an amended Norgrain voyage charterparty form that provided for the Owners to earn demurrage if the cargo operations exceeded the laytime allowed by the charterparty.

The vessel arrived at the Chinese discharge port, but, due to port congestion and limited storage space, discharge was delayed by 31 days.

The soybean cargo was found to contain mould and caking damage on discharge, in respect of which the Owners were exposed to a cargo claim under the bill of lading which they settled for about US$1.1m.

The Owners advanced claims against the Charterers in a London arbitration, claiming damages and/or an implied indemnity for this cargo liability. They argued that the Charterers’ failure to discharge within the agreed laytime period – in fact a prolonged retention on board the vessel – resulted in damage to this cargo, which would have been in a sound condition but for this delay.

Pursuant to section 45 of the Arbitration Act 1996, the parties asked the High Court to determine as a preliminary question of law whether the Owners could recover these damages from the Charterers or whether the Owners’ sole compensation for the Charterers’ failure to discharge within the allocated laytime period was demurrage (i.e. liquidated damages in a fixed amount).

Decision

Mr Justice Andrew Baker sought to determine “what it is that demurrage liquidates”. If the issue were free from authority, he would have considered that the Owners had the better of the argument by a clear margin. However, the governing authorities were contradictory, so he proceeded to consider them.

The Altus

In The Altus, the High Court found that damages were available to an owner in addition to demurrage, even if there was only one breach of contract. This decision cited the Court of Appeal’s judgment in Reidar v Arcos, in which an owner successfully claimed damages by way of deadfreight on top of demurrage.

The Bonde

Conversely, Mr Justice Potter in The Bonde stated that demurrage was an exhaustive remedy for a voyage charterer’s failure to load cargo within the agreed time period. Therefore, to obtain general damages in addition to demurrage, the owner had to establish “a breach additional to or separate from that of failing to load within the lays and/or at the agreed rate”. Mr Justice Potter argued he was supported in this approach by the decision in Reidar v Arcos, as informed by comments in Suisse Atlantique, on the basis that two breaches in that case were separate in law and therefore warranted two distinct heads of loss.

Clarification

Mr Justice Andrew Baker observed that the present case provided an “opportunity to resolve the long-standing uncertainty” which had arisen from these divergent approaches, and which is reflected in the leading textbooks, Scrutton on Charterparties and Voyage Charters.

In his view, the court had been wrong in The Altus to conclude that Reidar v Arcos was authority for the proposition that damages could be recovered in addition to demurrage for a single breach.

However, the court had also been wrong to conclude in The Bonde that Reidar v Arcos was authority for the contrary proposition, that such damages are not recoverable for a single breach – the judge considered that its reasoning was based on a misreading of Suisse Atlantique and should therefore not be followed.

Therefore, neither authority provided the answer, in the judge’s view.

On the basis of the agreed facts in this case, the Owners had suffered loss from the vessel’s prolonged detention at port:

Through the inability to use the vessel for subsequent transportation of freight; and
Through the cargo interests’ claims for the cargo damage.

Consequently, the judge decided that the Owners were entitled to claim both:

  • Demurrage (liquidated, fixed damages) for the vessel’s loss of earnings due to the delay; and
  • Damages for the loss flowing from the deterioration of the cargo (a by-product of the delay producing a different kind of loss).

Use this link to read the full article, authored by Athens Partner Evangelos Catsambas (pictured) and Gerard Rhodes, a trainee solicitor in our London office.

What is Maritime London?

Maritime London – the promotional body for UK based companies providing professional services to the international shipping industry

Funded by over 100 companies and organisations from a wide range of disciplines, Maritime London ensures that the UK remains a world beating location to base a maritime related business. Maritime London’s mission is to promote the UK as the world’s premier maritime business centre.

Our core Maritime Services

The UK is home to a world beating array of professional maritime service providers. Maritime sectors include:

© 2024 All Rights reserved. || Privacy/Terms